Millwoods Sewer Upgrade Phase I

Date

Client

TBD

Material

450mm Concrete Pipe 600mm Concrete Pipe

Location

Edmonton, Alberta

Crossing

Road Crossings

Geotechnical Condition

Clay Till

This Microtunnel work consisted of the installation of approximately 550 meters (1805 ft.) of 450mm and 600mm concrete sewer pipe through residential subdivisions and beneath arterial roadways at depths up to 12 meters (40 ft.).  The longest drive completed was approximately 110 meters (360 ft.) in predominantly clay till soil conditions.  The total duration of the projects was 3 months.