Edmonton International Airport Civil Utilities Phase I

Date

Client

Edmonton International Airport

Material

1800mm Reinforced Concrete Pipe

Location

Edmonton, Alberta

Crossing

Taxiway Runway

Geotechnical Condition

Clay Till

The work, undertaken as a subcontractor to Raywalt Construction, consisted of installation of approximately 220 meters (700 ft.) of 1800mm reinforced concrete pipe beneath Taxiway Alpha and Runway 12-30 at the Edmonton International Airport.  This project was particularly challenging as all typical airport activities remained operational during operations which lasted approximately six weeks.